Lay Down Area

Phase 1 involves preparations of the work site, such as demolishing buildings and other above-ground infrastructure, removal of the underground cables, and redirection of the gas pipelines. Temporary retaining walls are installed to ensure a stable situation and prevent landslides and/or subsidence and to enable the start of supply and storage of (construction) materials and on-site work preparation, such as the construction of the construction pit. The opening of the entrance road in December 2022 marked a successful completion of the first phase.

  • Removal of original buildings.
  • Removal of above-ground infrastructure.
  • Housing and parking possibilities.
  • Removal of underground cables and pipes.
  • Redirection of gas pipeline.
  • Removal of the tritium installation.
  • The construction of the PALLAS-reactor requires proper preparations. For example, the construction site will be levelled. For this purpose, part of the current dike will be flattened and excavated. The activities on and around the construction site also increase the load on the ground. Temporary retaining walls have therefore been installed.
  • Opening of the access road for construction traffic.

Ecology

The Energy & Health Campus is located next to the ‘Zwanenwater’ and ‘Pettemerduinen’, which are both nature reserves. All works have been carried out in accordance with the nature permit. Among other things, amphibian screens have been installed, bat boxes have been hung, and work is being carried out on the basis of an ecological work protocol. Ultimately, after construction is completed, the surrounding and natural values will be restored and, where possible, improved. Habitat for protected species will be added according to the protocol established with ecologists.

Lay down area
Lay down area
Phase 1
Pit & Foundation
Pit & Foundation
Phase 2
Building
Building
Phase 3
Completion
Completion
Phase 4