To enable the construction of the new reactor, various governmental bodies must take decisions on whether the project complies with the regulations, and they must issue the necessary permits. Below, you will find an overview of the permits in force and what their scope is. Other permits will be needed in the future and PALLAS is currently working on obtaining those.
Nature Act | construction and operation PALLAS area (Lay Down Area) |
Waterworks Act | drilling pipeline under the road N9 |
Province Regulation | intake constructions at Noordhollandsch Kanaal, drilling pipeline under the road N502, construction of temporary access road from Lay Down Area to the road N502 |
Water Act | Lay Down Area, secondary cooling system construction, PALLAS-reactor intake and discharge of water, building Pit & Foundation |
Soil Removal Act | Lay Down Area, secondary cooling system construction, PALLAS-reactor intake and discharge of water, building Pit & Foundation |
Nuclear Energy Act | reactor establishment |
Construction Act | PALLAS-reactor |
Zoning Plan | nuclear zoning PALLAS plot |